Building Information & Capital Improvements

Energy Savings Project (ESCO)

On February 27, 2018, the Braintree Town Council approved the implementation of an ESCO project for the Braintree School Department. This project will provide significant energy conservation measures to all six (6) of our elementary schools, the Monatiquot School Kindergarten Center, and Braintree High School. With the East Middle School MSBA supported core program project ready to start construction in June of 2018, and due to the MSBA's invitation to the Eligibility phase for South Middle School, these two buildings were intentionally not included in the ESCO scope of work.

Among the items being addressed in the ESCO project are:

  • installation of expandable Energy Management Control Systems that will modulate heating, cooling, and ventilation;
  • installation of new primary high efficiency boilers and back-up boilers in several buildings;
  • replacement of 45-year old transformers at Braintree High School;
  • new LED lighting fixtures and occupancy sensors;
  • walk-in cooler controls & high efficiency motors;
  • building weatherization; steam trap repairs and replacements, and
  • water conservation measures.

For and overview of the project, please click here: BPS ESCO Summary

Building Information

Click on the upward pointing arrow next to the name of the school to find information on each of our school buildings, including date of construction, overall square footage, the number of classrooms, as well as additional data. Within each building drop down, you will find a second upward pointing arrow labeled "Upgrades," which details projects done within each building and the year of completion.

Braintree High School

Braintree High School

128 Town Street
781-848-4000

Front of Braintree High School

Paved Parking Spaces: 621

Summary Value of Assets: $50,666,140

  • Building: 42,341,200
  • Yard Items: 136,900
  • Land (45.73 acres): 7,393,100
  • Furniture, Fixtures and Equipment: 784,940

Constructed: 1972

Square Footage: 380,847

Total Classrooms: 130

Enrollment: 1600

  • Grade 9: 400
  • Grade10: 368
  • Grade11: 377
  • Grade 12: 383
  • Special Needs: 72

Upgrades

  • Roof Installation, 1987
  • Public Address System Upgrade, 1997
  • Structural Building Repairs, 1997
  • Carpeting-Media Center, Guidance and Special Services Areas, 8 Classrooms (floor 3), 1997
  • 243 Student Lockers (floor 3), 1997
  • Exterior Lighting, 1997
  • Replacement of 1 Air Conditioning Unit, 1997
  • Fire Alarm System Upgrade, 1999
  • Repair of Gymnasium Bleachers, 1999
  • Student Furniture (4 classrooms), 1999
  • Conversion to Gas Burners, 1999
  • Repair of Concrete Plaza Deck, 1999
  • 160 Student Lockers (floor 3), 1999
  • Carpeting – main and gym foyers, choral, band and studio rooms, wellness center, 1999
  • Installation of security systems, 1999
  • Student lockers (gym), 2001
  • Air Conditioning, 2001
  • Carpeting (auditorium & media), 2001
  • Classroom furniture, 2001
  • File cabinets/teacher furniture, 2001
  • Paving and concrete repairs, 2001
  • Refinish gym floor, 2001
  • Renovate toilet facilities, 2001
  • Student lockers (400), 2001
  • Toilet facilities, 2002
  • Internet lab, 2002
  • Upgrade network servers, 2002
  • Installed 28 Math/Science lab computers, 2004
  • Installed 12 Photo lab computers, 2004
  • Cafeteria table replacement, 2005
  • Paving and concrete repairs (student, staff parking lots), 2005
  • Roof replacement – over rooms 319-311, 325-333 , 2005
  • Refurbished student lockers (400), 2005
  • Replaced 5 condensate boilers, 2005
  • Internet wiring in classrooms , 2005
  • Installed exterior signage – handicap accessibility, 2006
  • Installed interior signage – handicap accessibility, 2006
  • Replaced 2 roof top air handlers/air conditioning units, 2006
  • Roof replacement – over rooms 359-351, 2007
  • Refurbished electronics workshop into 2 classrooms, 2007
  • Refurbished bleachers, 2007
  • Converted mechanical drawing room into 2 science technology classrooms, 2007
  • Refurbished 8 4-way classrooms into 6 new classrooms, 2008
  • Refurbished language lab and installed new furniture, software and computers, 2008
  • Refurbished home economics room 283 into regular classroom, 2008
  • Roof replacement – over rooms 275-289, 303-341 , 2008
  • Replaced padlocks with combination spindle locks on 152 lockers, 2008
  • Upgraded “door ajar” alarm system, 2008
  • Painted gymnasium, 2008
  • Installed new lighting in gymnasium, 2008
  • Cafeteria table replacement, 2008
  • Remove asbestos fire curtain, 2009
  • Install new auditorium fire curtain, 2009
  • Auditorium air conditioning replacement, 2009
  • Auditorium carpet/renovation, 2009
  • Auditorium lighting systems, 2009
  • Auditorium seating replacement, 2009
  • Replaced 5 Airco boilers, 2009
  • Replaced all auditorium/stage doors, 2009
  • Install wrestling room padding, 2009
  • Install gymnastics rooms padding, 2009
  • Replace fitness center floor, 2009
  • Replace wrestling room floor, 2009
  • Tile replacement (registrar’s office, house 2, house 3), 2009
  • Replaced carpet auditorium foyer, 2009
  • Replaced carpet gymnasium foyer, 2009
  • Painted auditorium ceiling, 2009
  • Renovated sound and light booth, 2009
  • Replaced roof top air conditioning, 2010
  • Cafeteria table replacement, 2010
  • Repair/replace 21 water fountains, 2010
  • White board replacement, 2010
  • Oil tank removal, 2010
  • Carpet left side of media center, 2012
  • Elevator repair/replacement, 2012
  • Refurbish/replace cafeteria doors, 2012
  • Roof repair/replacement, 2012
  • White board replacement, 2012
  • Masonry repairs recoated exterior finish, 2013
  • Installed 7 additional exterior cameras, 2013
  • Refurbished boys locker rooms, 2014
  • Refurbished dance studio, 2014
  • Bathroom renovation, 2014
  • Renovate 7 Bathrooms, 2015
  • Replace gymnasium bleachers, 2015
  • Refurbish gymnasium floor, 2015
  • Repave front loop driveway and part of access road, 2015
  • Replaced roof top air conditioning unit, 2015
  • Solar PV on roof, 2016
  • Replaced carpeting in media center offices, 2016
  • Installed rolling steel door to loading dock, 2016
  • Repave back loop driveway and part of access road, 2016
  • Installed new kilns , 2016
  • Built new pre-school bathroom, 2016
  • Installed new walk-in freezer, 2016
  • New ceiling and lights (1st floor near elevators and locker area), 2016
  • Replaced carpet in both main lobbies, 2016
  • Replaced lockers, 2017

East Middle School

East Middle School

305 River Street
781-380-0170

Front of East Middle School

Paved Parking Spaces: 144

Summary Value of Assets: $16,573,830

  • Building: 9,964,900
  • Yard Items: 490,700
  • Land (46.19 acres): 5,679,200
  • Furniture, Fixtures and Equipment: 439,030

Constructed: 1961

Square Footage: 106,761

Total Classrooms: 47

Enrollment: 750

  • Grade 6: 248
  • Grade 7: 242
  • Grade 8: 233
  • Special Needs: 27

Upgrades

  • Roof installation, 1985
  • Conversion to gas, 1 boiler, 2 burners, removal of 1 oil tank, 1997
  • Replacement of front window Lexan with glass, caulked and painted frames, 1997
  • Refurbished auditorium seats, 1997
  • Refinishing of stage floor, 1997
  • Carpeting – auditorium, 1997
  • Replacement of front and sides of window Lexan with glass, 1998
  • Fire alarm system upgrade, 1999
  • Public address system upgrade, 1999
  • Replacement of auditorium roof, 1999
  • Replacement of bridge and remaining window Lexan, scraping and painting window frames, 1999
  • Installation of student elevator, 1999
  • Installation of security systems, 1999
  • 90 student chairs, 1999
  • Doors (original) 10 exterior, 2000
  • Roof replacement (academic wing), 2003
  • Roof repair/replacement (gymnasium, corridors, guidance, music areas), 2005
  • Paving and concrete repairs (curbing, sidewalks, and academic wing entrance), 2005
  • Grade 8 student lockers, 2005
  • Remove tile/refurbish rear bridge, 2005
  • Removed masonry walls, re-graded and landscaped, 2005
  • Renovate locker rooms, 2005
  • Upgraded 3 labs with additional memory (75 comp.), 2005
  • Internet wiring in classrooms, 2005
  • Installed exterior signage – handicap accessibility, 2006
  • Installed interior signage – handicap accessibility, 2006
  • Paving center courtyard, 2006
  • Granite curbing – front of school, 2006
  • Replaced 250 units of student furniture, 2007
  • Completely sanded and refinished gymnasium floor, 2007
  • Converted wood shop into 2 new classrooms with new lighting, ceilings and floors, 2008
  • Bleacher replacement, 2009
  • Student lockers, 2009
  • Refurbish elevator, 2010
  • Student lockers, 2010
  • New walk-in freezer, 2012
  • Paint interior, 2012
  • Re-pave front entrance, 2012
  • Window replacement (insulated glass), 2012
  • Installed air conditioning in office wing, 2013
  • Purchased 6 round cafeteria tables, 2013
  • Purchased 6 round cafeteria tables, 2014
  • Purchased 120 student desks and chairs, 2014
  • Purchased cafeteria tables, 2015
  • MSBA feasibility agreement, 2015
  • Converted 2 classrooms into 4 classrooms, 2015
  • Purchased additional student desks and chairs, 2015

South Middle School

South Middle School

232 Peach Street
781-380-0160

Front of South Middle School

Paved Parking Spaces: 55

Summary Value of Assets: $6,884,440

  • Building: 5,195,800
  • Yard Items: 70,100
  • Land (6.6 acres): 1,262,200
  • Furniture, Fixtures and Equipment: 356,340

Constructed: 1956, 2 modular classrooms added in 2001, 2 modular classrooms added in 2017

Square Footage: 88,364

Total Classrooms: 33

Enrollment: 646

  • Grade 6: 203
  • Grade 7: 220
  • Grade 8: 197
  • Special Needs: 26

Upgrades

  • Roof Installation, 1986
  • Fire alarm upgrade, 1988
  • Conversion to gas, 1 boiler, 3 burners, removal of 1 oil tank, 1997
  • Replacement of auditorium seats, 1997
  • Refinishing of stage floor, 1997
  • Replacement of front window Lexan with glass, caulked and painted frames, 1997
  • Replacement of front shades, 1997
  • Carpeting – auditorium , 1997
  • Replacement of front and sides of window Lexan with glass, 1998
  • Adult Chairs, 1999
  • Replacement of remaining window Lexan, scraping and painting of window frames, 1999
  • Roof installation, 1999
  • Installation of security systems, 1999
  • Public address system, 2000
  • Modular classrooms, 2001
  • Renovate toilet facilities/staff bathroom, 2002
  • Computer lab, 2002
  • Refinish gymnasium floor, 2003
  • Personal elevator, 2005
  • Replaced glass blocks with windows (gym, auditorium, and stairwells) , 2005
  • Grade 8 student lockers, 2005
  • Replacement of exterior doors, 2005
  • Internet wiring in classrooms, 2005
  • Installed exterior signage – handicap accessibility, 2006
  • Student furniture replacement – chairs, 2007
  • Installed new boiler, 2007
  • Installed new ceiling and lighting in cafeteria and adjacent classrooms, 2008
  • Installed new ceiling and lighting in room 118, 2008
  • Painted modular classrooms exterior, 2008
  • New auditorium stage lighting, 2009
  • Student lockers, 2009
  • Air condition office areas, 2010
  • Ceiling tiles and lighting replacement, 2010
  • Classroom furniture and equipment, 2010
  • Fire suppression system install/upgrade, 2010
  • Heating and ventilating retrofit, 2010
  • Paint interior, 2010
  • Upgrade electrical infrastructure/cabling, 2010
  • White board replacement, 2010
  • Window replacement (insulated glass), 2010
  • Installed walk-in freezer, 2012
  • Replaced all corridor floor tile, 2013
  • Auditorium refurbish, 2014
  • Replace kitchen floor tiles, 2016
  • Enlarged two classrooms , 2016
  • Added two modular classrooms, 2017
  • Created special ed classroom with bathroom, 2017
  • Paved front loop and sidewalks, 2017

Flaherty Elementary School

Flaherty Elementary School

99 Lakeside Drive
781-380-0180

Front of Flaherty Elementary

Paved Parking Spaces: 48

Summary Value of Assets: $3,506,230
  • Building: 2,813,100
  • Yard Items: 42,600
  • Land (12.5 acres): 522,700
  • Furniture, Fixtures and Equipment: 127,830

Constructed: 1953, 2006

Square Footage: 39,036

Total Classrooms: 22

Enrollment: 378

  • K: 22
  • Grade 1: 22, 21, 23
  • Grade 2: 20, 21, 19
  • Grade 3: 16, 21, 20
  • Grade 4: 19, 22, 20
  • Grade 5: 18, 18, 26, 19
  • Special Needs: 8, 11, 6, 6

Upgrades

  • Roof installation, 1992
  • Fire alarm upgrade, 1995
  • 1 gas burner conversion – oil tank removed, 1996
  • Windows (classroom), 1997
  • Completion of window replacement, 1998
  • Installation of security system, 1999
  • Completion of design plans for aluminum window trim installation, 1999
  • Public address system, 2000
  • Paving and concrete repairs/new parking area and road, 2002
  • Refinish gymnasium floor, 2002
  • Mobile computer lab with 30 laptop computers, 2005
  • Painted school exterior, 2005
  • Door replacement , 2005
  • Installed exterior signage – handicap accessibility, 2006
  • Internet wiring in classrooms, 2006
  • Constructed 2 additional classrooms, 2006
  • Installed all steel ramps for handicap accessibility, 2007
  • Completed repairs to boiler room – flooding damage, 2007
  • Purchased and installed handicap accessible stage lift, 2008
  • Air conditioned entire building except for gymnasium/cafeteria, 2008
  • Installed new ceiling and lighting in both classroom corridors, 2008
  • Installed sink in teachers’ room, 2008
  • Replaced ceiling in teacher’s room, 2009
  • Installed all new unit ventilators, 2009
  • Installed sound proof door on stage, 2010
  • Refurbished room 18 into 3 learning spaces, 2010
  • Stage door installation (sound proof), 2010
  • Fire suppression system upgrade, 2010
  • Purchase 30 student desks and chairs, 2014
  • Add a bathroom for a special needs classroom, 2015
  • Renovate staff bathroom, 2015
  • Replace exterior doors, 2015
  • Pave and fence in playground for special ed program, 2015
  • Installed a new men's ADA bathroom, 2016
  • Created a classroom from the media center, 2016
  • Replaced floor tiles in half of the school, 2017
  • Installed new shed for the playground, 2017

Highlands Elementary School

Highlands Elementary School

144 Wilwood Avenue
781-380-0190

Front of Highlands Elementary

Paved Parking Spaces: 41

Summary Value of Assets: $6,472,120

  • Building: 4,046,700
  • Yard Items: 105,700
  • Land (4.8 acres): 2,090,900
  • Furniture, Fixtures and Equipment: 228,820

Constructed: 1930, addition in 1953, addition in 1968, 2 modular classrooms added 2001

Square Footage: 42,806

Total Classrooms: 20

Enrollment: 386

  • K:
  • Grade 1: 20, 19, 21, 20
  • Grade 2: 17, 18, 17, 18
  • Grade 3: 18, 19, 18, 18
  • Grade 4: 23, 22, 22, 22
  • Grade 5: 18, 19, 19, 18

Upgrades

  • Roof installation, 1990
  • Fire alarm upgrade, 1989
  • Replace windows in 1930 section, 1998
  • Installation of security system, 1999
  • Completion of design plans for aluminum window trim installation, 1999
  • Replace Lexan (new section) in windows, 2000
  • Public address system, 2000
  • Renovate toilet facilities, 2000
  • Modular classrooms, 2001
  • Playground paving, 2003
  • Paving and concrete repairs (staff parking lot, sidewalks, and circular driveway), 2005
  • Re-landscaped playground with turf, 2005
  • Painted interior of building, 2005
  • Installed exterior signage – handicap accessibility, 2006
  • Internet wiring in classrooms, 2006
  • Furniture replacement for 2 classrooms, 2007
  • Installed new flag pole, 2008
  • Installed new tilt skillet in kitchen, 2009
  • Oil tank removal, 2010
  • Replace gym floor/refurbish walls, 2010
  • Oil tank removal, 2012
  • Wooden door replacement, 2012
  • Masonry repairs – original building, 2012
  • Paint exterior – original building, 2012
  • Window replacement, 2012
  • Fire suppression system upgrade, 2012
  • Purchase 28 student chairs and 22 student desks, 2014
  • Cafeteria floor and ceiling tile replacement, 2014
  • Remove and replace floor tiles on the second floor, 2015
  • Replace exterior doors, 2015
  • Replace gym floor , 2015
  • Install new boiler, 2015

Hollis Elementary School

Hollis Elementary School

482 Washington Street
781-380-0128

Front of Hollis Elementary

Paved Parking Spaces: 76

Summary Value of Assets: $6,794,000

  • Building: 4,766,300
  • Yard Items: 0
  • Land (2.66 acres): 1,158,700
  • Furniture, Fixtures and Equipment: 869,000

Constructed: 1912, addition in 1955, lower level renovation in 2006

Square Footage: 53,698

Total Classrooms: 24, 4

Enrollment: 428

  • K: 19
  • Grade 1: 14, 15, 15, 15
  • Grade 2: 17, 18, 17, 18
  • Grade 3: 15, 13, 14, 15
  • Grade 4: 18, 19, 20, 18
  • Grade 5: 21, 21, 22, 21
  • Special Needs: 8, 8, 7, 16, 11, 13

Upgrades

  • Roof installation, 1992
  • Fire alarm system upgrade, 1992
  • Gas burner conversion – oil tank removed, 1998
  • Paving, 1994
  • Window replacement, 1994
  • Public address system upgrade, 1994
  • Replacement of glass blocks with weather proof panels, 1998
  • Installation of security system, 1999
  • Completion of design plans for aluminum window trim installation, 1999
  • Renovate toilet facilities, 2002
  • Window repairs, 2002
  • Refinish gymnasium floor, 2005
  • Exterior preservation repairs (original school), 2005
  • Renovated storage area into art classroom , 2005
  • Installed exterior signage – handicap accessibility, 2006
  • Boiler rebuild, 2006
  • Renovated lower level into 4 additional classrooms, boys and girls bathrooms, and staff bathrooms (Rental Income), 2006
  • Internet wiring in classrooms , 2006
  • Installed new trophy case, 2008
  • Installed 5 new classroom air conditioners, 2008
  • Installed new boiler, 2008
  • Flag pole refurbished and lit, 2008
  • Refurbish 1st floor hallway (original building), 2009
  • Replaced boiler, 2009
  • Bathroom renovation – original building, 2012
  • Window replacement/vinyl trim, 2012
  • Fire suppression system upgrade, 2012
  • All exterior trim painted, 2013
  • Purchase 25 student desks and chairs, 2014
  • Install new ceiling tiles and lights, 2015
  • Replace exterior doors, 2015
  • Refinished and repaired classroom floors, 2016
  • Replaced steam pipes, 2016
  • Replaced steam pipes, 2017
  • Enlarged nurse's room, 2017

Liberty Elementary School

Liberty Elementary School

49 Proctor Road
781-380-0210

Front of Liberty

Paved Parking Spaces: 42

Summary Value of Assets: $4,615,795

  • Building: 3,269,900
  • Yard Items: 36,200
  • Land (5.05 acres): 1,130,500
  • Furniture, Fixtures and Equipment: 179,195

Constructed: 1957, addition in 1964, addition in 2006

Square Footage: 34,163

Total Classrooms: 22

Enrollment: 436

  • K
  • Grade 1: 18, 17, 16, 16, 18
  • Grade 2: 22, 20, 21, 21, 22
  • Grade 3: 17, 17, 18, 18
  • Grade 4: 22, 21, 21, 21
  • Grade 5: 22, 23, 23, 22

Upgrades

  • Roof installation, 1988
  • Fire alarm upgrade, 1993
  • Public address system, 1997
  • Installation of security system, 1999
  • Doors – 4 exterior, new hardware front, 2000
  • Replace window Lexan with glass, caulk and paint frames, 2001
  • Conversion burner/replace boiler, 2002
  • Replace windows, 2002
  • Additional parking added, 2003
  • Removed oil tank, 2003
  • Walkways paved, 2003
  • Mobile computer lab with 30 laptop computers, 2004
  • Installed exterior signage – handicap accessibility, 2006
  • Installed interior signage – handicap accessibility, 2006
  • Constructed 2 additional classrooms, 2006
  • Installed custom cabinetry and student furniture for 2 classrooms, 2006
  • New bathroom partitions in boys bathroom, 2006
  • Internet wiring in classrooms, 2006
  • Installed new operable windows in 50% of the classrooms and the entire cafeteria, 2008
  • Completely sanded and refinished cafeteria floor, 2008
  • Baseball field irrigation/refurbishing, 2009
  • Window replacement, 2009
  • Door replacement/gymnasium, 2010
  • Install new gymnasium lights, 2010
  • Gymnasium floor installation, 2010
  • New gymnasium sound system, 2010
  • New stage curtains, 2010
  • Paint gymnasium, 2010
  • Replaced all corridor floor tile, 2013
  • Install new ceiling tiles and lights, 2015
  • Remove and replace floor tiles, 2016
  • Created new media center and small group space, 2016
  • Paved front driveway and parking lots, 2017

Morrison Elementary School

Morrison Elementary School

260 Liberty Street
781-380-0230

Front of Morrison Elementary

Paved Parking Spaces: 53

Summary Value of Assets: $4,275,340

  • Building: 3,319,100
  • Yard Items: 0
  • Land (14.60 acres): 700,900
  • Furniture, Fixtures and Equipment: 255,340

Constructed: 1968

Square Footage: 52,000

Total Classrooms: 21

Enrollment: 400

  • K: 20
  • Grade 1: 21, 21, 22, 21
  • Grade 2: 20, 20, 21, 19
  • Grade 3: 23, 19, 23
  • Grade 4: 22, 21, 20
  • Grade 5: 20, 20, 20
  • Special Needs: 10, 9, 8

Upgrades

  • Roof installation, 1992
  • Public address system, 1997
  • Replacement of window Lexan with glass, caulked and painted frames, 1997
  • Installation of security systems, 1999
  • Fire alarm upgrade, 1999
  • Paving and concrete repairs, 2001
  • Removed oil tank , 2005
  • Added additional staff parking, 2005
  • Installed exterior signage – handicap accessibility, 2006
  • Internet wiring in classrooms , 2006
  • Installed new tilt skillet in kitchen, 2009
  • Air conditioning installation (interior rooms), 2010
  • Installed new gymnasium floor, 2010
  • Painted gymnasium, 2010
  • Window replacement, 2012
  • Replace exterior doors, 2015
  • Paved driveway, 2016
  • Replace carpet in the media center and repaint, 2016

Ross Elementary School

Ross Elementary School

20 Hayward Street
781-380-0240

Front of Ross Elementary

Paved Parking Spaces: 40

Summary Value of Assets: $3,627,770

  • Building: 2,376,700
  • Yard Items: 30,700
  • Land (6.8 acres): 1,105,000
  • Furniture, Fixtures and Equipment: 115,370

Constructed: 1951

Square Footage: 35,412

Total Classrooms: 15

Enrollment: 267

  • K:
  • Grade1: 17, 17, 18
  • Grade 2: 17, 19, 18
  • Grade 3: 18, 18, 18
  • Grade 4: 19, 21, 20
  • Grade 5: 16, 16, 15

Upgrades

  • Roof installation, 1988
  • Fire alarm upgrade, 1989
  • 1 gas burner conversion – oil tank removed, 1987
  • Installation of security system, 1999
  • Replace public address system, 2000
  • Traffic signal, 2001
  • Ventilation repairs, 2002
  • Retaining wall (remove & re-grade), 2002
  • Window replacement, 2002
  • Refinish gymnasium floor, 2003
  • Installed exterior signage – handicap accessibility, 2006
  • Internet wiring in classrooms, 2006
  • Boiler replacement, 2007
  • Replaced all windows on front and 2 sides of the building, 2008
  • Replaced all glass blocks with operable windows, 2008
  • Window replacement, 2009
  • Floor tile/carpet replacement/media center, 2010
  • Stage curtain installation, 2010
  • Stage floor refinish, 2010
  • Gymnasium painting, 2012
  • Paved staff parking area, 2013
  • Install new ceiling tiles and lights, 2015
  • Replace classroom rug with tile floor, 2015
  • Pave driveway and west parking lot, 2015
  • Replaced floor tiles in half of the school, 2017

Monatiquot School Kindergarten Center

Monatiquot School Kindergarten Center

25 Brow Avenue
781-380-0220

Front of Monatiquot

Paved Parking Spaces: 30

Summary Value of Assets: $3,182,280

  • Building: 2,095,700
  • Yard Items: 11,300
  • Land (2.89 acres): 946,900
  • Furniture, Fixtures and Equipment: 128,380

Constructed: 1954, addition in 1962

Square Footage: 23,060

Total Classrooms: 13

Enrollment: 289

  • Full Day K: 22, 26, 24, 20, 22, 30
  • 1/2 Day K: 6, 38, 18, 47, 8, 21
  • Special Needs: 7

Upgrades

  • Roof installation, 1992
  • Public address system upgrade, 1999
  • Installation of security system, 1999
  • Upgrade fire alarm system (original), 2000
  • Refinish gym floor, 2002
  • Boiler installation, 2010
  • Oil tank removal, 2012
  • Telephone system and computer upgrades and installation, 2014
  • Install security cameras, 2014
  • Purchase student and teacher furniture for 10 classrooms, 2014
  • Bathroom refurbishing, 2014
  • Floor tile replacement, 2014
  • Window replacement, 2014
  • Replaced gym/cafeteria lights, 2015
  • Installed ceiling fans in gym, 2016
  • Installed new stage curtains, 2017